TVA reports $1.7B in payments from unnamed data center under new large-load tariff
The federal utility's tariff charges about $1.5 million per MW of requested capacity above 5 MW, and the rate may change for future customer cohorts, TVA said in an SEC filing.
What happened
The Tennessee Valley Authority (TVA) is a federal power utility. It says one data center customer will pay it $1.7 billion in total. The customer is not named. The deal falls under a new pricing plan for data centers that use more than 5 megawatts (MW) of power.
Why it matters to you
Data centers use large amounts of electricity. How utilities price that power affects who pays for new plants and grid upgrades, and TVA warns that cost pressures could push up power rates.
The takeaway
TVA now charges big data centers a set fee for the capacity they reserve, and it has landed a $1.7 billion deal under that plan.
By the numbers
TVA reports a $1.7B payment under its new large-load tariff
- $1.7BUnnamed data center's total payment
- $1.5MCharge per MW requested above 5 MW
- $13BTVA capital investment, three years
What it means for you
TVA has a construction permit from the NRC for a BWRX-300 small modular reactor at Clinch River, but has not decided whether to build it.
Data centers above 5 MW in TVA territory face a capacity charge of about $1.5 million per MW, and the rate may differ for later cohorts.
TVA's filing reports a $13 billion three-year capital plan and warns that inflation and tariff pressures will persist into 2027, which could increase pressure on power rates.