Mitsubishi Heavy CEO says off-grid costs will push data centers back to utilities

Utilities and independent power producers made up 94% of MHI's new gas turbine orders in 2024 and 2025, CEO Eisaku Ito told analysts on Nov. 6.

Illustrative photo: yellow fibre optic cables plugged into a patch panel
Illustrative photo: yellow fibre optic cables plugged into a patch panel Photo by Albert Stoynov on Unsplash

What happened

Many U.S. data center operators say they will build their own power plants, off the grid. Mitsubishi Heavy Industries (MHI), a major maker of gas turbines, says that plan will cost too much. Its CEO expects data centers to connect to the regular power grid over time.

Why it matters to you

If he is right, the cost of powering AI would stay tied to utilities, which means the electric grid and the bills customers pay would carry more of the growth.

The takeaway

MHI's CEO bets that cost will bring data centers back to the power grid.

What it means for you

If you build software

Ito says smaller gas plants cost more to run than larger utility-scale combined cycle plants, a factor for teams weighing off-grid power.

If you run a business

Data center operators planning their own generation face a running-cost gap that MHI expects to push them toward grid connections.

If you invest

MHI reports an 80% rise in Energy Systems profit, a 37 GW turbine backlog and about $3.1 billion in planned capacity spending, and says it has had no order cancellations in two years.