Harvard study ties 403 US hyperscale data centers to 25.7M tons of CO2 in one year

The Nature Sustainability study estimates the sites used 82 TWh, about 1.8% of US electricity, and that roughly 54% of that power came from fossil fuels.

What happened

Researchers at Harvard studied 403 very large US data centers, the buildings that run cloud and AI services. They estimate the electricity these sites used from May 2024 to April 2025 was linked to 25.7 million metric tons of carbon dioxide. The amount depends on how the local power grid makes its electricity.

Why it matters to you

Data centers draw power from the same grids that serve homes and businesses. Where they are built, and what fuels the local grid, affects emissions and local air quality.

The takeaway

How much pollution AI causes depends heavily on the power sources behind the data centers.

What it means for you

If you build software

Power capping, carbon-aware scheduling and better cooling are available now, but lead author Gianluca Guidi says efficiency may not cut total use if demand grows faster.

If you run a business

Operators reporting low emissions through PPAs and certificates may face county or city targets that use the actual local grid mix.

If you invest

IDC analyst Dan Versace expects US data center emissions to more than double by 2030 and demand to outpace clean supply through at least 2028.