Developers plan 100+ off-grid gas plants for US data centers, 115 GW in total, Cleanview says

Only 4.9 GW of the planned behind-the-meter gas capacity is operating and 15.8 GW is under construction, according to Cleanview data cited by MIT Technology Review.

By the numbers

Planned US behind-the-meter gas capacity far exceeds what is operating

  • Planned capacity (GW)115
  • Under construction (GW)15.8
  • Operating (GW)4.9
Cleanview data, as reported by MIT Technology Review

What happened

Data centers need huge amounts of electricity. Connecting to the power grid can take years. So some developers are building their own natural gas power plants next to the data center, a setup called "behind the meter."

Why it matters to you

These plants could raise greenhouse-gas emissions and push up natural gas prices, which can affect household heating and cooking bills.

The takeaway

Companies building AI data centers are choosing speed over cleaner power, and the costs could reach other people.

What it means for you

If you build software

Few planned on-site plants will use combined-cycle turbines, so expect less efficient single-cycle designs, and pairing gas with renewables or storage could cut how often plants fire.

If you run a business

Energy Innovation's Matthias Fripp says more gas demand could raise natural gas prices, which could raise rates for the roughly 60% of US households that use gas for heating and cooking.

If you invest

Developers are paying a premium to get online faster, and only a small fraction of announced capacity is built or under construction, according to Cleanview.