Belgium orders Google to halt work on Aiseau-Presles datacentre, 300 workers told to stop
Wallonia officials say the three-hectare building is almost finished though its modified permit was revoked in August. A report goes to prosecutors.
Step by step
How the Aiseau-Presles datacentre permit dispute unfolded
- 2025: Google appliesGoogle applied to merge two datacentres into one and switch to liquid cooling.
- April: Change approvedRegional authorities approved the change.
- August: Permit revokedMinister François Desquesnes revoked it over drought concerns after residents appealed.
- 7 January: Council rulingBelgium's council of state ruling is expected on Google's appeal.
What happened
Belgian authorities told Google to stop building a very large datacentre in the south of the country. A datacentre is a building full of computers that run online services and AI. Officials say Google kept building even though its permit had been refused.
Why it matters to you
Datacentres use large amounts of energy and water, and local residents are pushing back on where and how they are built.
The takeaway
Google must stop construction in Belgium while the permit dispute is unresolved.
What it means for you
Cooling design choices, such as drawing river water instead of air cooling, can decide whether a permit survives local review.
Companies planning large facilities face permit risk and possible stoppages if they build ahead of final approval.
Google faces a halted site in Belgium and a criminal investigation in Finland, and a court ruling is due on 7 January.